John Day Dam Turbine Runner Replacement and Generator Rewind Project-100% Review

Key Details
Buyer
DEPT OF DEFENSE
Notice Type
Presolicitation
NAICS
237990
PSC
Z2KA
Due Date (Hidden)
Next 30 days
Posted Date (Hidden)
Past year
Key Dates
Posted Date
September 13, 2024
Due Date
April 5, 2024
Place of Performance
OR
Sam.gov Link
Link
Description

13 September 2024:  The Government intends to issue the solicitation package for the John Day TRGR procurement in late January 2025.  Please note this timeframe is subject to change and this information is for planning purposes only.  Please continuously monitor SAM.gov for additional updates.  We do not intend to issue another draft solicitation for industry review prior to issuing the official solicitation package.

22 May 2024:  Basic FAR provision 52.222-33 Notice of Requirement for Project Labor Agreement and basic FAR clause 52.222-34 Project Labor Agreement will be included in the solicitation once issued.   

24 April 2024:  Regarding the biological and turbine performance, the Government is aware that some performance targets may not be met and will actively compete with other performance targets, but these are targets and not guarantees. The Government has refined its criteria on fatigue stresses for water filled hubs, which could impact biological and turbine performance. The runaway speeds will also be updated in the final solicitation package.  Please see attachment Draft Turbine Performance 48 13 13.01 26 . 

To maintain the integrity of the acquisition, please contact only Ms. Randolph or Mr. Liebzeit with any comments or questions regarding this draft solicitation posting.    

22 March 2024:  The Government intends to issue the solicitation package for the John Day TRGR procurement in October 2024.  Please note this timeframe is subject to change and this information is for planning purposes only.  Please continuously monitor SAM.gov for additional updates. 

11 March 2024:  The PLA request for input date has been extended from 13 March 2024 to 05 April 2024 by close of business.  

28 February 2024:  Please see the attached Project Labor Agreement (PLA) request for input and please respond on or before 13 March 2024.  The updated response date is only applicable to this PLA input request.  

12 January 2024:  The Government intends to issue the solicitation package for the John Day TRGR procurement in August 2024.  Please note this timeframe is subject to change and this information is for planning purposes only.  Please continuously monitor SAM.gov for additional updates.  We do not intend to issue another draft solicitation for industry review prior to issuing the official solicitation package.   

13 October 2023:  The existing runner geometry file is available upon written email request to Aragon Liebzeit at Aragon.N.Liebzeit@USACE.army.mil  This file is for information only and the Government makes no guarantees regarding the accuracy of the file. 

23 October 2023:  The geometry in the provided model is the fluid and the runner geometry can be taken from the interior boundary surfaces of the model.

29 November 2023:  A new file in .stp format of the runner geometry is available upon request.  

Due Date (Hidden)
Next 30 days
Posted Date (Hidden)
Past year