Schedule 1 will include dredging of approximately 820,000 Cubic Yards (CYs) of the Mouth of Colorado Entrance Jetty Channel and Detention Basin and will include varying advanced maintenance and 2' over-depth. Material will be placed west of west/south Jetty in nearshore zone; Construction of Terminal Groin and 4 of the 5 planned nearshore breakwaters at Sargent Beach, 25 miles east of the Mouth of Colorado. Estimate duration is 270 Calendar Day (CD) for construction of groin and breakwaters and 90 CD for dredging. And 3 Options for beach placement and construction of 5th nearshore breakwater.
Placement of material will include both beach placement and upland confined placement.
Sources Sought attached fur further informaiton.