Q&A 2
Is the goal with the volumetric calculations of the containments to certify them or just to inspect and conduct the volume calculations? (It is to inspect and provide calculations demonstrating the containment area has sufficient capacity in accordance with 40 CFR 112.)
Q & A
RE: Question for Solicitation W9128F25Q0010 DUG
Answer: For API external inspections, the KTR doesn’t have to empty the tank.
DLA-Energy has requested USACE conduct API 653 External inspections at Dugway Proving Grounds, UT on Tanks 4056, 4057, 5660 & 5661 in accordance with all laws standards, federal regulations, as well as any state and local regulations and guidelines.
See attachments for more details.