PROJECT: AK PFH 58(1), Neck Lake Rd. Reconstruction: NPOWI Hwy.to Marine Access Facility Jct.
LOCATION: 45 miles NW of Coffman Cove, Hyder Census Area, Prince of Wales Island, Alaska
WORK: Work consists of roadway excavation, sub-excavation, soft ground embankment construction (surcharge), grading, rock blasting, riprap placement, rockery, drainage (including large Aquatic Organism Pipes), embankment (including settlement monitoring), placement of aggregate surface course, guardrail installation, erosion control, temporary traffic control, permanent signage, and turf establishment. See “Project Description” posted under attachments for additional details.
LENGTH:
Schedule A – 1.6 miles of road reconstruction
Schedule B – 2.0 miles of road reconstruction
Schedule C – 2.4 miles of road reconstruction
TENTATIVE COMPLETION DATE: Fall 2026
CONTRACT TYPE: Sealed Bid, Firm-Fixed-Price
ESTIMATED PRICE RANGE: Between $10,000,000 and $20,000,000
INTERESTED VENDORS LIST: To view the Interested Vendors List, you must register as a SAM user, be logged in, and linked to an entity. If you are signed into SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract Opportunities Administrator role for your entity in SAM.gov. If you need assistance, call the Federal Service Desk at 866-606-8220.
THIS SOLICITATION IS OFFERED FOR FULL AND OPEN COMPETITION ON AN UNRESTRICTED BASIS
This project is anticipated to be solicited Winter 2024/2025
This project will include 3 bid schedules. Only one schedule will be awarded.
PRELIMINARY PLANS and a letter with additional project information are in electronic format only and are posted with this synopsis. To ensure you receive notification when the solicitation documents are posted to SAM.gov, please click on the “follow” button at the top of the opportunity page. When solicitation documents are issued, the INVITATION FOR BIDS (specifications and plans) will be posted at this link.