REPAIR BUOY YARD
This is a construction (service) requirement to perform a topographic survey and prepare the specified grading plan; temporarily relocate/demo storage sheds/containers; demo the HAZMAT area; demo perimeter fencing and vegetation; strip and stockpile RCA and RAP surface treatments for reuse; strip existing asphalt and remove, regrade and repair area per the grading plan; compact the subgrade; demo and relocate the storage container underground electrical service; place geotextile and geogrid reinforcement; backfill with compacted imported base course and grade; install asphalt and concrete pavement; install stockpiled RCA and RAP surfaces; install replacement perimeter fencing and HAZMAT fencing, load and seed disturbed areas; and reinstall storage sheds/containers.
Construction of the Buoy Yard will be performed in two phases to provide continued U.S. Coast Guard access to the Buoy Yard equipment laydown and storage areas. Phase 1 will occur first and includes all work specified as outlined in the drawings. Phase 2 will begin after the completion of Phase 1 and will consist of the remaining portions of the work. Mobilization will not occur until April, 2025 at the earliest in order to help minimize impacts associated with cold weather concreting. This requirement is not part of the USCG Standardization Program.